Monday 28 May 2012

Chimney Dismantling


Churchill have successfully completed the piecemeal small dismantling of a 50m tall x 2.2m diameter disused steel chimney on a COMAH 1 site in Stowmarket.

To add to the complexity of the project that would see a requirement for hot work at height the chimney was situated adjacent to a live railway line managed by Network Rail that determined cranes could not be used as part of the project.

The chimney was dismantled within budget and completed within an eight week program