Monday 20 April 2009

Concrete Chimney Refurbishment

A 60k project to refurbish 2no 45m reinforced concrete chimneys at The University of East Anglia has been completed within program and within budget by Churchill Steeplejacks (UK) Ltd

The project was completed over a twelve week period with a three man team in attendance and included the replacement and repair of the capping arrangements, concrete repairs to each windshield, lightning protection upgrade and the application of a protective paint system.

A steel support framework was also installed around the summit of both chimneys to provide structural support to the upper regions of each windshield.

The cold weather conditions experienced during January and February 2009 delayed the application of the paint product which required temperatures of 5 degrees and rising, following the completion of the contract the chimney windshields will remain free of maintenance for at least the next seven year period.



No comments: