Chimney Inspections

The inspection of single flue industrial chimneys is regulated by the HSE document GS53 and the ATLAS guidance booklet that builds upon the HSE document GS53.

The self supporting single flue steel chimney has commonly been used for a period in excess of 35 years during which time many have seen a change over from serving coal to oil through to the modern day gas fired boilers. This change over in fuels has left its own legacy creating very corrosive environments, this coupled with the effects of the UK climate has led to a large number of this type of structures ultimately failing, hence the HSE Guidance Note GS 53 was published in 2001.

For multi flue industrial steel chimneys the inspection guidance issued for single flue steel chimneys does not apply, the inspection of a steel multi flue chimney i.e where the waste gases do not come into direct contact with the main supporting structure, is covered in Appendix A of BS 4076 :1989.

At present there is currently no inspection guidance for concrete or brick chimneys, however due to the harsh environments and processes related to their use it is prudent to regularly inspect concrete and brick chimneys to ensure they remain in a serviceable condition.

A chimney inspector must be able to prove competency and experience with a minimum preference of being industry qualified via the NVQ route.

Wednesday, 7 April 2010

Work at Height Hierarchy of Risk

Via risk assessment the use of a mewp to facilitate access to structures should always be the access method of choice particuarly for the completion of surveys.

In the uk truck mounted MEWPS can provide access up to working heights upwards of 70 metres.

During a recent meeting between the hse and the steeplejack federation ATLAS the hse voiced their concerns into the mindset of the steeplejack industry in relation to risk assessments for working at height and our industries continued insistance to survey structures using traditional ladders as apose to MEWPS.

Wherever it is practicable to do so Churchills always look to employ MEWPS for completing surveys of structures up to 70 metres, unfortunetly industry as a whole needs educating in relation to the Work at Height Regs it is only then that the additional cost for the use of MEWPS will become broadly accepted.

Thursday, 25 March 2010

Money vs Safety

Can it really be true that in difficult financial times money men are potentially placing their employers at risk?

During the recent financial climate as an organisation who supply to many blue chip organisations, councils and government establishments throughout the UK it has been very disconcerting and somewhat alarming to witness the swing in the ethos of many in relation to the awarding of their contracts on a heavily cost weighted basis.

The steeplejack & lightning protection industry has taken huge strides in recent years to improve both it’s professionalism and quality of service within the construction sector, in the main this has been achieved by a change in the mindset of business owners with particular emphasis being placed on training and development and also a reduction in the amount of sub contractor labour otherwise known as ‘price work’.

All the hard work and gains made by many in our sector is now seriously under threat as the money men within awarding organisations look to cut costs by awarding contracts seemingly compromising on the level of training achievement and accreditation that is otherwise available.

The steeplejack sector in particular has long been an industry where little encouragement is required for those businesses less willing to train and achieve to take full advantage of such an opportunity, a fact that many of the long established steeplejack business will echo.
The outcome? - Sadly whilst those companies’s in our sector who have failed to invest in the development of their business benefit from an increase in activity those who have invested heavily in their business are left fighting a battle for contracts and as part of that battle face an uphill challenge in convincing the money men of the folly of their ways.

A tender recently received by Churchill’s issued by a UK council stated that the tender evaluation process would consist of 60% cost & 40% ability, in the world we live and in particular in our potentially high risk sector should the aforementioned ratios stated in the councils tender not require exchanging?

Tuesday, 8 December 2009

OHSAS 18001 2007

In theory the attainment of OHSAS 18001 2007 should serve to provide a springboard for any organisation to expand their market share via clearly being able to demonstrate to potential clients their proven and documented approach to health & safety in the work place.

However the sad truth is that organisations including blue chips fail to fully grasp the importance of such an accreditation and those that do are slow to promote a preference to working with companies who have achieved OHSAS 18001 2007 throughout their organisation.

This can be vey frustrating, listening on one hand to organisations promoting their values and approach to H&S but in reality experiencing their failings in ensuring companies holding such accreditations are actively promoted from within.

The most frustrating scenario is the one of familiarity, often large blue chips operate as satellites and the selection of a contractor can often be purely based on experience e.g having used a particular company for years.

Regardless of this Churchill Steeplejacks are still very proud to be the first Steeplejack company to be accredited to this standard.

Friday, 1 May 2009

Churchills Accreditation

A total of ten Churchill Steeplejacks operatives have successfully achieved the SSSTS accreditation for site supervision.

This level of commitment to training will ensure that all Churchill sites will have the construction industry requirement in relation to on site supervision. Add to this the following minimum requirement for a Churchill Steeplejacks (UK) Ltd site based team and our clients have arguably one the most highly trained and qualified workforces at their disposal;

The following are all managed by a team consisting of two NEBOSH in construction departmental managers

SSSTS
CSCS Industry Gold Card
CCNSG Passport to Safety
Quarry Passport
NVQ Level 2 Steeplejack/Lightning Protection Engineers
NVQ Level 3 Advanced Steeplejack
IPAF
Confined Space Working
NDT Dye Penetrant Testing
Abrasive Wheels
Mobile Towers
Safety Harness Inspection
PAT Testing
LOLER Equipment Testing
Appointed Person
Asbestos Awareness
Rescue & Recovery at Height
Slinger/Banksman
First Aid
Safe Earth Testing
Safe Road Digging

Monday, 20 April 2009

Concrete Chimney Refurbishment

A 60k project to refurbish 2no 45m reinforced concrete chimneys at The University of East Anglia has been completed within program and within budget by Churchill Steeplejacks (UK) Ltd

The project was completed over a twelve week period with a three man team in attendance and included the replacement and repair of the capping arrangements, concrete repairs to each windshield, lightning protection upgrade and the application of a protective paint system.

A steel support framework was also installed around the summit of both chimneys to provide structural support to the upper regions of each windshield.

The cold weather conditions experienced during January and February 2009 delayed the application of the paint product which required temperatures of 5 degrees and rising, following the completion of the contract the chimney windshields will remain free of maintenance for at least the next seven year period.



Tuesday, 14 April 2009

Steel Chimney Emergency Callout

A steel chimney located at Eastwood Comprehensive School in Nottinghamshire fell victim of the strong winds that hit the county during the earlier hours 23rd March 2009.

Churchills received an emergency call out request from the school who feared the chimney was in imminent danger of falling over, Churchills dispatched a three man team to site together with a mobile crane and successfully dismantled the chimney just in time to preventing it falling into classrooms below.

Once the chimney had been successfully dismantled Churchills then set about arranging for the manufacturer and installation of a temporary smaller chimney section to be fitted to the remaining base section of the chimney to ensure the school could continue to provide hot water and therefore remain open.

From receiving the emergency call all of the aforementioned work was safely completed within a 12 hour period.

This was possible due to Churchills possessing in house Crane Appointed Persons who were able to plan and manage the lifting operations with minimum notice coupled with our fabrication capacity.

These photographs depict the chimney in it's precarious position upon our arrival to site.

The importance of the inspection and maintenance of this type of insulated steel chimney has been recognised by the Health & Safety Executive who together with the steeplejack federation A.T.L.A.S have issued guidance notes detailing a thorough inspection criteria. Unfortunately whilst this particular chimney had been regularly inspected it would appear that the inspector had not completed the survey in accordance with the aforementioned recommendations.



Wednesday, 1 April 2009

SPECIALISTS IN HIGH RISE DEMOLITION & STRUCTURAL MAINTENANCE

In 2004 Churchill Steeplejacks (UK) Ltd were awarded the contract to complete the external refurbishment of a115m tall concrete cooling tower at Ratcliffe On Soar Power station.

Following the successful completion of the contract that saw Churchills provide, install and maintain all motorised access cradles and complete the contract with no sub contract element the contract was extended for the following four year period to include 6 of the 8no cooling towers at Ratcliffe on Soar.

Each cooling tower project involved up to 12 operatives working on a tower at any one time from the motorised access platforms suspended from the summit of the tower

One of the biggest challenges faced was how to ensure safe access and egress for all operatives working on the tower together with ensuring systems for effectively rescuing and recovering operatives within a twelve minute period from any position on the tower were in place at all times. This was successfully achieved via the deployment of a full time rope access team positioned on the scaffold at the summit of the tower.

Over 56000 man hours were engaged and in excess of 5000 temporary anchor locations were installed to complete the six towers, all being completed within program, within budget and most importantly without incident.

Suspended Access Platforms in operation


Installation of access scaffold around the full circumference





Friday, 16 January 2009

Pectel Group in Administration

The Pectel Group formed in 1982 entered into administration 12th December 2008 becoming Churchill Steeplejacks (UK) Ltd largest debtor since the formation of the company in 1994.

On the day Churchills completed extensive decommissioning work to the disused 45m concrete boiler chimney at the University Hospital Birmingham administrators Zolfo Cooper of Manchester were called in.

Formed in 1982 as an asbestos removal firm the growth of the Pectel Group saw them include no fewer than 12 Limited companies at the time they entered into administration with over 250 employees nationwide.