In December 2008 Churchills were appointed directly by e-on and mobilised to site to commence with the removal and replacement of 2no 110m tall brick flues housed within a 107m tall concrete windshield.
The removal of both brick linings was completed through the Christmas holidays to ensure a hand over date of March 2009 remained achievable.
During the removal of the brick linings the internal cast concrete ring beams that supported the internal brickwork at regular intervals throughout their height were found to have eroded beyond repair. Working with e-on engineers Churchills designed replacement ring beam supports to be installed in conjunction with the re bricking of both vertical flues.
Exposed to some of the coldest temperatures in recent years and now having to work night shifts through January, February and March to remain on programme Churchills installed internal access platforms to facilitate the re building of both flues and completed on time and within budget.
Showing posts with label dismantling. Show all posts
Showing posts with label dismantling. Show all posts
Wednesday, 1 July 2009
Friday, 1 May 2009
Churchills Accreditation
A total of ten Churchill Steeplejacks operatives have successfully achieved the SSSTS accreditation for site supervision.
This level of commitment to training will ensure that all Churchill sites will have the construction industry requirement in relation to on site supervision. Add to this the following minimum requirement for a Churchill Steeplejacks (UK) Ltd site based team and our clients have arguably one the most highly trained and qualified workforces at their disposal;
The following are all managed by a team consisting of two NEBOSH in construction departmental managers
SSSTS
CSCS Industry Gold Card
CCNSG Passport to Safety
Quarry Passport
NVQ Level 2 Steeplejack/Lightning Protection Engineers
NVQ Level 3 Advanced Steeplejack
IPAF
Confined Space Working
NDT Dye Penetrant Testing
Abrasive Wheels
Mobile Towers
Safety Harness Inspection
PAT Testing
LOLER Equipment Testing
Appointed Person
Asbestos Awareness
Rescue & Recovery at Height
Slinger/Banksman
First Aid
Safe Earth Testing
Safe Road Digging
This level of commitment to training will ensure that all Churchill sites will have the construction industry requirement in relation to on site supervision. Add to this the following minimum requirement for a Churchill Steeplejacks (UK) Ltd site based team and our clients have arguably one the most highly trained and qualified workforces at their disposal;
The following are all managed by a team consisting of two NEBOSH in construction departmental managers
SSSTS
CSCS Industry Gold Card
CCNSG Passport to Safety
Quarry Passport
NVQ Level 2 Steeplejack/Lightning Protection Engineers
NVQ Level 3 Advanced Steeplejack
IPAF
Confined Space Working
NDT Dye Penetrant Testing
Abrasive Wheels
Mobile Towers
Safety Harness Inspection
PAT Testing
LOLER Equipment Testing
Appointed Person
Asbestos Awareness
Rescue & Recovery at Height
Slinger/Banksman
First Aid
Safe Earth Testing
Safe Road Digging
Tuesday, 14 April 2009
Steel Chimney Emergency Callout
A steel chimney located at Eastwood Comprehensive School in Nottinghamshire fell victim of the strong winds that hit the county during the earlier hours 23rd March 2009.
Churchills received an emergency call out request from the school who feared the chimney was in imminent danger of falling over, Churchills dispatched a three man team to site together with a mobile crane and successfully dismantled the chimney just in time to preventing it falling into classrooms below.
Once the chimney had been successfully dismantled Churchills then set about arranging for the manufacturer and installation of a temporary smaller chimney section to be fitted to the remaining base section of the chimney to ensure the school could continue to provide hot water and therefore remain open.
From receiving the emergency call all of the aforementioned work was safely completed within a 12 hour period.
This was possible due to Churchills possessing in house Crane Appointed Persons who were able to plan and manage the lifting operations with minimum notice coupled with our fabrication capacity.
These photographs depict the chimney in it's precarious position upon our arrival to site.
The importance of the inspection and maintenance of this type of insulated steel chimney has been recognised by the Health & Safety Executive who together with the steeplejack federation A.T.L.A.S have issued guidance notes detailing a thorough inspection criteria. Unfortunately whilst this particular chimney had been regularly inspected it would appear that the inspector had not completed the survey in accordance with the aforementioned recommendations.


Churchills received an emergency call out request from the school who feared the chimney was in imminent danger of falling over, Churchills dispatched a three man team to site together with a mobile crane and successfully dismantled the chimney just in time to preventing it falling into classrooms below.
Once the chimney had been successfully dismantled Churchills then set about arranging for the manufacturer and installation of a temporary smaller chimney section to be fitted to the remaining base section of the chimney to ensure the school could continue to provide hot water and therefore remain open.
From receiving the emergency call all of the aforementioned work was safely completed within a 12 hour period.
This was possible due to Churchills possessing in house Crane Appointed Persons who were able to plan and manage the lifting operations with minimum notice coupled with our fabrication capacity.
These photographs depict the chimney in it's precarious position upon our arrival to site.
The importance of the inspection and maintenance of this type of insulated steel chimney has been recognised by the Health & Safety Executive who together with the steeplejack federation A.T.L.A.S have issued guidance notes detailing a thorough inspection criteria. Unfortunately whilst this particular chimney had been regularly inspected it would appear that the inspector had not completed the survey in accordance with the aforementioned recommendations.


Wednesday, 1 April 2009
SPECIALISTS IN HIGH RISE DEMOLITION & STRUCTURAL MAINTENANCE
In 2004 Churchill Steeplejacks (UK) Ltd were awarded the contract to complete the external refurbishment of a115m tall concrete cooling tower at Ratcliffe On Soar Power station.
Following the successful completion of the contract that saw Churchills provide, install and maintain all motorised access cradles and complete the contract with no sub contract element the contract was extended for the following four year period to include 6 of the 8no cooling towers at Ratcliffe on Soar.
Each cooling tower project involved up to 12 operatives working on a tower at any one time from the motorised access platforms suspended from the summit of the tower
One of the biggest challenges faced was how to ensure safe access and egress for all operatives working on the tower together with ensuring systems for effectively rescuing and recovering operatives within a twelve minute period from any position on the tower were in place at all times. This was successfully achieved via the deployment of a full time rope access team positioned on the scaffold at the summit of the tower.
Over 56000 man hours were engaged and in excess of 5000 temporary anchor locations were installed to complete the six towers, all being completed within program, within budget and most importantly without incident.
Suspended Access Platforms in operation
Following the successful completion of the contract that saw Churchills provide, install and maintain all motorised access cradles and complete the contract with no sub contract element the contract was extended for the following four year period to include 6 of the 8no cooling towers at Ratcliffe on Soar.
Each cooling tower project involved up to 12 operatives working on a tower at any one time from the motorised access platforms suspended from the summit of the tower
One of the biggest challenges faced was how to ensure safe access and egress for all operatives working on the tower together with ensuring systems for effectively rescuing and recovering operatives within a twelve minute period from any position on the tower were in place at all times. This was successfully achieved via the deployment of a full time rope access team positioned on the scaffold at the summit of the tower.
Over 56000 man hours were engaged and in excess of 5000 temporary anchor locations were installed to complete the six towers, all being completed within program, within budget and most importantly without incident.
Suspended Access Platforms in operation
Thursday, 26 March 2009
Churchill Steeplejacks Obtain CSCS Platinum Standard
Churchill Steeplejacks UK Ltd are the proud recipients of the CSCS Platinum Award that recognises a companies achievement in attaining more than a 90% ratio of it's workforce being CSCS accredited card holders.
Churchills have achieved the highest award available from CSCS with a 100% attainment level for it's employees with not one of the 40no cards being a minimum general workers accreditation and with all being industry related.
Boasting 2no NEBOSH in construction departmental managers, 12no SSSTS site based Operatives and one of only 2no NVQ level 3 Steeplejack assesors/trainers in the country this recognition by CSCS highlights further the companies passion for training it’s staff ensuring we possess the most highly trained, skilled and qualified workforce operating in our sector.
Churchills have achieved the highest award available from CSCS with a 100% attainment level for it's employees with not one of the 40no cards being a minimum general workers accreditation and with all being industry related.
Boasting 2no NEBOSH in construction departmental managers, 12no SSSTS site based Operatives and one of only 2no NVQ level 3 Steeplejack assesors/trainers in the country this recognition by CSCS highlights further the companies passion for training it’s staff ensuring we possess the most highly trained, skilled and qualified workforce operating in our sector.
Subscribe to:
Posts (Atom)